DPWH, NEA to finalize compensation guidelines for electric pole relocations
- September 3, 2024
- 0
We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
The cookies that are categorised as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ...
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Performance cookies are used to understand and analyse the key performance indexes of the website which helps in delivering a better user experience for the visitors.
Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.
The Department of Public Works and Highways (DPWH) and the National Electrification Administration (NEA), with the approval of the Department of Energy (DOE), are set to collaborate on developing a compensation formula for the relocation of electric poles impacted by various government infrastructure projects.
In a report by Manila Bulletin, this proposed compensation framework would be discussed during a consultation scheduled for September 5, as part of the ongoing updating of the Joint Circular initially signed by the DPWH and DOE in 2017, and subsequently updated in 2019 and 2021.
Data by NEA revealed that 53,017 poles owned by electric cooperatives (ECs) have already been relocated to accommodate the government’s infrastructure expansion, with relocation costs estimated to exceed Php 4.3 billion.
Draft Circular No. 4, nearing finalization by the DPWH and DOE, mandates collaboration between NEA and DPWH to guarantee the swift and thorough relocation of distribution facilities that could interfere with national road projects, streamlining infrastructure development across the country.
As part of the agreed compensation formula, NEA will also oversee the spending of funds from the DPWH to the ECs. Furthermore, NEA will assist ECs in seeking regulatory support to recover costs not covered by the compensation provided under the joint guidelines.
Meanwhile, in cases where ECs delay or fail to relocate electric poles impacted by government projects, NEA will be responsible for enforcing appropriate actions against the utilities involved.
Additionally, NEA is required to submit biannual reports to the DOE, DPWH, and both houses of Congress on the progress of the relocation of obstructing distribution facilities and the payment of compensation to ECs.