EDC to spend P7 billion for plant rehabilitation
- May 9, 2017
- 0
We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
The cookies that are categorised as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ...
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Performance cookies are used to understand and analyse the key performance indexes of the website which helps in delivering a better user experience for the visitors.
Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.
Most of the capital expenditure this year will be allotted for the rehabilitation of the 112.5 – megawatt (MW) Tongonan geothermal plant in Leyte, EDC president and COO Richard Tantoco said.
“That’s our major capex this year. Our capex is about P7 billion. Around P3 billion will be for Tongonan,” Tantoco said.
The two units of the Tongnan plant will shut down for 110 consecutive days.
“But then, there’s change in the whole turbines, some of the foundations, everything. So our drilling cost in the future and our work over cost are going to contract, it will have an increase output by 10 MW, decrease in steam consumption by nine percent,” Tantoco said.
He added that the retrofit of the two units are on track and set to be completed by the third quarter. “After the retrofit, it will be as good as new and we expect an increase of up to 10 percent in its total capacity.”
EDC is also set to optimize its 125-MW Upper Mahiao geothermal plant this year with a budget of P400 – 500 million, EDC vice president for corporate finance Erwin Avante said.
Tantoco said that the plant’s turbines will be replaced with newer metallurgy.
“The first one is in, the second one has gone in, third and fourth are arriving October and in March next year. That will be much much higher chrome, some titanium. We expect those machines to be really robust going forward,” he said.
The efficiency upgrade reliability improvement came after the company lost P600 million in opportunity cost following the tripping of the Tongonan plant two years ago, and the Upper Mahiao plant last year.
“Within this year or next year, you’ll see generation getting better. But you will really have everything kicking in on a full year basis in 2018. This is a transition year with a lot of outages,” Tantoco said.