Citicore Seeks ERC Approval to Link 90MW Pangasinan Solar to Grid
- April 11, 2025
- 0
Citicore Solar Pangasinan Inc. (CSPI) has submitted an application to the Energy Regulatory Commission (ERC) to develop a dedicated point-to-point transmission facility for its 90MW Sta. Barbara 1 Solar Power Project in Pangasinan. The propo
The project includes a plant switchyard and a 500-meter, 69-kV double-circuit transmission line, costing PHP 176.1 million, fully funded by CSPI. “Given the RE Law’s objective to accelerate the development of the country’s renewable energy resources and increase the utilization of renewable energy, it is in the interest of the government to help RE developers such as the Applicant to achieve commerciality and commence operations at the soonest practicable time,” the application stated.
CSPI has also requested confidentiality for its third-party Facilities Study, citing proprietary data.
The company
The ERC will hold a virtual hearing on May 8, 2025, to assess the application. Stakeholders can submit comments or petitions to intervene by May 3, 2025.
How do you view CSPI’s effort to bring its solar project online? Share your thoughts in the comments!
Follow Power Philippines on Facebook and LinkedIn for more updates.