Customise Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorised as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyse the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.

No cookies to display.

June 19, 2025
News

Meralco Enhances Grid Reliability in Quezon with New High-Capacity Transformer

  • April 20, 2025
  • 0

Manuel V. Pangilinan-led Manila Electric Company (Meralco) has upgraded the power transformer at the Tayabas Delivery Point (DP) Substation from 100 megavolt-amperes (MVA) to 300 MVA. This strategic

Meralco Enhances Grid Reliability in Quezon with New High-Capacity Transformer

Manuel V. Pangilinan-led Manila Electric Company (Meralco) has upgraded the power transformer at the Tayabas Delivery Point (DP) Substation from 100 megavolt-amperes (MVA) to 300 MVA. This strategic move will address the growing power demand in Quezon and nearby towns in Laguna.

Located in a fast-developing area, the upgraded 230kV–115kV substation now offers N-1 contingency and supports high load growth, making Meralco’s distribution system more resilient. The upgrade is also expected to reduce system loss by an estimated 168,691.32 kilowatt-hours.

The new transformer enhances power reliability for a wide range of key establishments, including Tayabas Community Hospital Inc., Southern Luzon State University, ACE Medical Center Sariaya, Primark Town Center Tayabas, Pacific Mall Lucena, Quezon Medical Center, Lucena MMG General Hospital, the Quezon Provincial Governor’s Office, and SM City Lucena.

Meralco said the transformer upgrade would also enable the substation to accommodate additional load applications in the future, supporting the continued development of Quezon and surrounding areas.

“The uprating of the Tayabas power transformer is just one of the many projects we have lined up to enhance the reliability and capacity of our distribution system. Projects like this enable us to continue providing safe, stable, and sufficient power to homes, businesses, and vital institutions in fast-developing areas like Quezon Province,” said Froilan J. Savet, Meralco First Vice President and Head of Networks.

“As energy demand continues to grow, we remain dedicated to building a resilient distribution network that is capable of supporting economic development that ultimately improves the lives of Filipinos,” Savet added.