After much delay, the Department of Energy (DOE) is looking to kickstart the commercial operations of the Wholesale Electricity Spot Market (WESM) Mindanao by the..
Tag Archives: Mindanao-Visayas Interconnection Project
The Energy Regulatory Commission (ERC) gave its go signal for the National Grid Corporation of the Philippines’ (NGCP) Cebu-Bohol 230-kilovolt (kV) interconnection project. In its..
Hurdles involving resistance from landowners and issuance of permits from several local government units have further pushed the launch of the Mindanao-Visayas Interconnection Project (MVIP)..
Electricity rates may continue to increase as an effect of the continuous rise of international coal prices. Estimates from the Philippine Independent Power Producers Association..
The commercial operations of the Wholesale Electricity Spot Market (WESM) in Mindanao has been postponed once again to coincide with the completion of the Mindanao-Visayas..
Major players in the Philippine energy sector are in agreement in recognizing Mindanao’s huge potential to develop and even provide power to other parts of..
The Independent Electricity Market Operator of the Philippines (IEMOP) sees no shortage in power supply while the Malampaya gas field suspends production from October 2-22...
The National Grid Corporation of the Philippines (NGCP) is looking to finish the Mindanao-Visayas Interconnection Project (MVIP) within the first quarter of 2022. During the..
The National Grid Corporation of the Philippines (NGCP) is working to repair one of its high-voltage submarine cables connecting Negros and Cebu damaged three weeks..
The completion of the National Grid Corporation of the Philippines’ (NGCP) Mindanao-Visayas Interconnection Project (MVIP) may extend beyond its adjusted December 2021 target, as several..