First Gen plants resume operations
- April 20, 2017
- 0
We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
The cookies that are categorised as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ...
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Performance cookies are used to understand and analyse the key performance indexes of the website which helps in delivering a better user experience for the visitors.
Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.
Restoration work on the San Lorenzo Switchyard has been complete, First Gen Corp. said.
“We are pleased to advise that the connection to the grid of the 500-megawatt (MW) San Lorenzo, 414 MW San Gabriel, and 97 MW Avion power plants has been restored. Accordingly, power output from all three power plants can now be exported to the grid,” they said.
The switchyard connects the company’s three natural gas-fired power plants to the National Grid Corporation of the Philippines’ transmission lines.
“We exerted all efforts to enable San Lorenzo, San Gabriel, and Avion to export their outputs at the quickest time. Our site management team and our contractors have worked tirelessly since last week including through the Holy Week,” First Gen vice president Jerome Cainglet said.
The 1,000-MW Sta. Rita power plant resumed operations after assessment showed that the switchyard did not suffer any damages, First Gen earlier announced.
The Luzon grid’s power supply thinned last week after power facilities tripped due to the earthquake that hit Batangas in April 8.
NGCP placed the grid on yellow alert from 9 am to 4 pm, but raised the red alert status from 1 pm to 3 pm after power demand increased during the supply insufficiency.