May 15, 2026
News

Malampaya Phase 4 advances subsea works as project moves toward first gas

  • May 5, 2026
  • 0
Malampaya Phase 4 advances subsea works as project moves toward first gas

The Malampaya Phase 4 (MP4) project is progressing with subsea installation and pipelaying works offshore Palawan, marking a pivotal step toward integrating new gas resources into the country’s primary natural gas facility.

The development follows the successful completion of a drilling campaign under Service Contract No. 38, which confirmed two new gas resources from the Malampaya East-1 and Camago-3 wells. These discoveries are expected to support continued production from the Malampaya gas field.

Offshore construction activities have advanced with the installation of critical subsea infrastructure, including flowlines that will connect the newly drilled wells to the existing Malampaya production system.

A major milestone was the installation of a Flowline End Terminal (FLET), which serves as a connection point between subsea pipelines and production facilities. The equipment was installed at a depth of approximately 690 meters, enabling the safe and efficient transport of natural gas from the new wells.

Installation works were carried out by offshore construction vessels Audacia and Fortitude. Audacia completed the laying of flowlines for the Malampaya East and Camago wells, while Fortitude installed supporting subsea components such as foundations, protective mattresses, and other auxiliary equipment.

In a technical first for the project, 30-meter piles were successfully driven into the seabed at around 1,100 meters water depth using hydraulic hammering technology, highlighting the complexity of the offshore works.

The subsea pipelaying activities also mark the first deepwater offshore pipe installation in the Philippines since 2000, signaling renewed activity in the country’s offshore energy sector.

“Recent milestones from drilling to subsea installation reflect the steady advancement of Malampaya Phase 4 toward full system integration,” said Prime Energy.

To further strengthen the subsea system, umbilicals—used for power supply, communication, and hydraulic control—are scheduled to be installed in the coming months.

The project will then move into the commissioning and hook-up phase, which includes pressure testing, nitrogen drying, and the installation of subsea jumpers to connect the wells to the main production system.

Malampaya Phase 4 remains on track to deliver first gas by the fourth quarter of 2026. Once completed, the project is expected to extend the productive life of the Malampaya field by an estimated six years.

The Malampaya project is a key component of the Philippines’ energy supply, providing about 20% of Luzon’s electricity. The continued development of the gas field is seen as critical in sustaining power generation as existing reserves decline.

How critical is the timely completion of Malampaya Phase 4 in securing the Philippines’ future energy supply?

Follow Power Philippines on Facebook and LinkedIn or join our Viber community for more updates.