DOE: PH needs 53 GW to achieve 2040 RE target
- April 8, 2024
- 0
We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.
The cookies that are categorised as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ...
Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.
Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.
Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.
Performance cookies are used to understand and analyse the key performance indexes of the website which helps in delivering a better user experience for the visitors.
Advertisement cookies are used to provide visitors with customised advertisements based on the pages you visited previously and to analyse the effectiveness of the ad campaigns.
The Department of Energy (DOE) shares that the country is 53 gigawatts (GW) way in reaching its 2040 renewable energy (RE) capacity target.
Energy Assistant Secretary Mylene C. Capongcol said that the target was seven times the current capacity of 8,264 megawatts (MW). As of the moment, the country would need around 53 gigawatts (GW) of additional RE capacity by 2040, which would have equated to 175 terawatt hours (TW) of generation.
In a Business World article, the DOE said it was able to raise the renewable portfolio standards (RPS) program’s demand for on-grid electricity producers from 1% to roughly 2.52% in 2022.
RPS mandated distribution utilities, retail electricity suppliers, and generation firms to procure a chunk of their supply from qualified RE sources.
Capongcol continued, saying that the Clean Energy Scenarios 1 and 2’s inclusion of nuclear energy has yet to be included in the RE target.
In addition to RPS, the DOE has been implementing initiatives such as the Green Energy Auction Program (GEAP), creating a policy framework for offshore wind, and allowing 100% foreign ownership of RE projects.
The assistant secretary added that the department had been working on a revised omnibus guideline for the conferment of service contracts.
Around 1,282 RE contracts with a total potential capacity of 130.3 GW have been awarded by the DOE as of January.