MERALCO: Power interruptions in Metro Manila, Laguna from April 2 to 7

Senate seeks probe on Luzon power interruptions

Manila Electric Company (MERALCO) has announced that certain areas in Metro Manila and Laguna will face temporary power interruptions this week due to maintenance activities.

Maintenance and upgrading operations are scheduled in specific locations from April 2 to April 7, said MERALCO’s Head of Corporate Communications Joe Zaldarriaga.

According to a Philippine Daily Inquirer report, Zaldarriaga clarified that these activities are part of routine maintenance efforts, typically involving a few areas each day rather than widespread outages.

Zaldarriaga further explained that only select areas or municipalities need to temporarily disconnect from electricity service due to new pole installations. He said de-energizing or power removal is a necessary part of the installation process.

MERALCO has provided a schedule of areas expected to experience power interruptions from April 2 to April 7.

April 2 – 3 – Makati City

Between 11:00 PM and 11:30 PM (April 2) and then between 3:30 AM and 4:00 AM (April 3)

  • Portion of Amorsolo St. from Gamboa St. to Antonio Arnaiz Ave. including Adelantado St.; and First Global Building in Legazpi Village, Bgy. San Lorenzo.
  • Portion of Antonio Arnaiz Ave. from Don Chino Roces Ave. to and including WalterMart Makati, Nihonbashitei and Salesiana Publishers in Bgys. Pio Del Pilar and San Lorenzo.
  • Portion of Don Chino Roces Ave. from Don Bosco Press to and including The Beacon Makati in Legazpi Village, Bgy. San Lorenzo.

Between 11:00 PM (April 2) and 4:00 AM (April 3)

  • Portion of Antonio Arnaiz Ave. from Amorsolo St. to near Don Chino Roces Ave. including St. John Bosco Parish Church, The Beacon Amorsolo Tower 3 and Don Bosco Pugad Center in Legazpi Village, Bgy. San Lorenzo.

April 3 – Diliman, Quezon City

Between 8:30 AM and 9:00 AM and then between 3:00 PM and 3:30 PM

  • Portion of Gen. Luna St. from Maria Felipe St. to Magsaysay St. in Tierra Pura Subd.
  • Portion of Magsaysay St. from Congressional Ave. to Via Hilario St. including Roxas Ave. and Osmeña St. in Tierra Pura Subd. and Saling Lahi Subd. Phase 1.; Via Pisa and Via Ramgo Sts. in Villa Firenze Subd.
  • Portion of Pura Villanueva St. from Teodoro M. Kalaw St. to near N. Ramirez St. in Tierra Bella Subd.
  • Portion of Luciano Estrada St. from Pura Villanueva Kalaw St. to Via Ramgo St. in Tierra Bella Subd.
  • Portion of Salvador Estrada St. from Demetria Reynado St. to P. Quiambao St. in Tierra Bella Subd.
  • Portion of Valerio Kalaw St. from Pura Villanueva Kalaw St. to near Demetrio Reynado St. in Tierra Bella Subd.

Between 9:00 AM and 3:00 PM

  • Portion of Gen. S. Aquino St. from near Lopez Jaena St. to Gen. Malvar St. in Tierra Pura Subd.
  • Portion of Gen. Malvar St. from Gen. S. Aquino to Maria Felipe St. in Tierra Pura Subd.
  • Portion of Maria Felipe St. from Gen. Malvar St. to Gen. Luna St. in Tierra Pura Subd.

April 3 – Laguna

Between 9:00 AM and 12:00 PM

  • The whole of Doña Consuelo Village (Medex Corp. Subdivision) and Maharlika Village along Maharlika Highway in Barangay San Francisco

April 4 – Laguna

Between 9:00 to 3:00 PM

  • Parts of Biñan

April 4 – 5 – Alabang and Pasig

Between 9:00 PM (April 4) and 2:00 AM (April 5)

  • Parts of Muntinlupa

Between 10:00 PM (April 4) and 3:00 AM (April 5)

  • Parts of Pasig City

April 7 – Quezon City

Between 9:00 AM to 2:00 PM

  • Parts of Diliman